Front
Explain how a DAN is used to update contractors and engineers about modifications to the project design or construction methods. (5 marks)
Back
1. Structured Communication of Modifications
  • Process: DANs formally communicate any approved design or construction method changes to contractors and engineers. Each DAN outlines the specific changes, reasoning, and any new procedures required, ensuring clarity in expectations.
  • Impact: This structured communication minimizes misunderstandings and ensures that all field teams have a clear, standardized reference for implementing modifications​​.
2. Detailing Technical Requirements and Procedural Adjustments
  • Process: DANs specify technical requirements (e.g., new support configurations or material specifications) and detail any procedural adjustments (e.g., changes in excavation sequence or additional safety protocols).
  • Impact: By detailing these requirements, DANs help contractors and engineers understand the exact implementation requirements, allowing them to adjust workflows effectively and maintain project alignment​​.
3. Establishing Accountability and Tracking Implementation
  • Process: Each DAN requires sign-off from relevant parties, creating accountability for implementing the specified changes. It also serves as a record that can be reviewed during audits or quality checks.
  • Impact: This accountability ensures that contractors and engineers follow through on updates, with clear responsibility for compliance. Tracking progress on DANs supports ongoing project quality and adherence to revised designs​.